Bewilligende Stelle INTERREG V

The contracting authority provides the contracts for the project lead partners in the INTERREG V-programme Germany-Netherlands, based on the decision of the steering committee. The lead partner receives from the contracting authority a contract which contains the financing from different sources. This simplifies the financial management of the project. By creating a legal relation, a possibility for formal complaints by projects is provided.

Project
Information

Planned project costs

1.200.000,00 €

Project Duration

5.12.2014 - 31.12.2022

Priority

technical assistance

Lead Partner

Bezirksregierung Münster

Project
Financing

Financer Amount
Bezirksregierung Münster 0,00 €
MB Niedersachsen 100.964,92 €
Ministerie van Economische Zaken en Klimaat 227.171,21 €
EFRE / EFRO 629.753,92 €
MWIDE NRW 242.109,95 €